The plan's commitments

183 actions across 7 sectors

Every action names the departments leading it and, for most, a target year. Implementation status arrives with the first annual reporting cycle; until then this is the plan as adopted.

11 of 183 actions match. Lead department: SF County Transportation Authority.

Transportation 11

  1. 1-3

    Advance major long-term transit capital projects and programs, including: SFMTA, SFCTA

    • Muni Metro Modernization Program: enter project development phase for Federal Transit Administration (FTA) Core Capacity grant, complete installation of Train Control Upgrade Project initial technology demonstration and begin subway replacement and on-street technology installation. SFMTA
    • The Portal: obtain and execute a Full Funding Grant Agreement from the FTA and begin construction to extend Caltrain service from Fourth and King Street to the Salesforce Transit Center. SFMTA, SFCTA
    • Connect SF Transit Strategy Geary/19th Avenue Subway: complete pre-environmental phase. SFMTA, SFCTA
    • Bayview Caltrain Station: complete environmental phase and secure funding for subsequent phases. SFCTA

    No date set

  2. 2-10
  3. 2-11
  4. 2-12
  5. 2-7
  6. 3-4
  7. 3-6
  8. 4-10
  9. 4-6
  10. 4-7
  11. 4-9